PicTraff(1).png
300WAreaMap.png
pic.png
8/19/24 Update Traffic Route

300 West Road Reconstruction

300 West Construction Update 8/28/2024

Construction is scheduled to be completed by October 1st

Please watch for new traffic routes and detours as construction progresses.

 

300 West construction progress update:

Asphalt from 4900 S. to 4400 S. Complete

Remove and replace the subgrade from 4400 S. to the Riverdale border. Complete

 

What’s next?

Asphalt from 4400 S. to the Riverdale border 9/3rd-4th

Raise the Manholes and water valves from 4400 S to Riverdale border 9/5

Open 4400 S. to traffic 9/6

Close 5000 S 300 W intersection 9/9

Remove and replace subgrade from 4900 S. to 5000 S.

Install new curb and gutter and sidewalk

Asphalt from 4900 S. 5000 S.

Raise Manholes and water valves between 4900 S. 5000 S.

 

 

Update 8/19/2024

Please watch for new traffic routes and detours as construction progresses.

300 west roadway reconstruction progress updates:

  • Storm Drain installation is nearly complete
  • Subgrade and asphalt between 4900 S. to 4400 S. is complete
  • ADA ramps, curb and gutter and sidewalk complete between 4900 S to 4400 S

 

What’s next:

  • Remove and replace the subgrade and asphalt from 4400 S. to the Riverdale border
  • Remove and replace the curb and gutter, driveways and sections of the sidewalk between 4900 S. and 5000 S.
  • Install subgrade between 4900 S. to 5000 S
  • Asphalt 4900 S to 5000 S.

 

Update 7/9/2024

As everyone knows, road construction and underground utility work can be challenging with unforeseen obstacles that may slow performance down. Preparing for these obstacles helps the construction crews stay on schedule while managing all the challenges that come with construction.

 

300 West Roadway Reconstruction Progress to date:

  • Excavated and removed the subgrade material between 4400 S. to 5000 S.
  • Installed the structural fabric and structural fill for the road subgrade between 4400 s. to approximately 4900 S.
  • Started ADA ramp removal and prep for replacement
  • Installed storm drainpipe between 4850 S. to 4800 S.

 

What’s next:

  • Continue installing the subgrade between 4400 S. to 5000 S.
  • Remove and replace the storm drainpipe between 4800 S. to 5000 S.
  • Continue to remove and replace ADA ramps.

Removing and replacing the storm drainpipe may restrict driveway access during the day in the area. For your safety and others please plan accordingly as construction crews are working as quick and efficient as possible.

Thank you for your cooperation and patience with making this a successful project.

 

300 WEST RECONSTRUCTION PROJECT OVERVIEW

The 300 West roadway from 5000 South to the Riverdale border. (approx. 4300 South) is scheduled to be replaced starting June 10, 2024 and is anticipated to be completed by October 1st, 2024.

300 West is a main corridor through Washington Terrace. It is highly traveled and requires a high level of maintenance. Reconstructing 300 West will ensure longevity, safety, and reduce future repair costs.

The scope of the project will include:

  • Removing and replacing the asphalt road section. This will require excavating out approximately 14” of the road and replacing it with structural file and new asphalt.
  • Replacing various sections of curb and gutter to improve surface drainage.
  • Replacing various sections of sidewalk and eliminating trip hazards.
  • Replacing ADA approaches to meet the ADA standards.
  • Upgrading the storm drain piping between 5000 South and 4800 South to provide better storm water drainage in the area.

Reconstructing 300 West is going to be a major project that will require several road closures and detours throughout the project. Resident and emergency vehicle access will be maintained during construction. Residents will be notified by door hanger of any construction that may deny access to your residence.

Project Funding

The estimated cost to complete this project is $3.7 million dollars. The City has received a federal grant to support much of the overall project cost, meaning that the City will be responsible for only 7.25% of the estimated cost. These funds will come from utility fees and other general funds.

 

Q.     When is construction scheduled to start?

A. Construction is scheduled to start April 1st (weather permitting).

 

Q.      When is the project scheduled to be completed?

A. The project is scheduled to be completed by October 1st, 2024.

 

Q. Will I be able to access my driveway during construction.

A. Yes, although sections of the road will be closed to thru traffic, local resident and emergency vehicle access will remain during construction. If construction denies access to your driveway, you will be notified by a city representative and/or an information door hanger.

 

Q.     Can I park on the street during construction?

A. For the safety of your vehicle and the construction crew on the street parking will be restricted during construction.

 

Q. Will I receive my mail and deliveries during construction?

A. Yes, the post office will be able to deliver your mail and packages. If your mailbox is not accessible an attempt will be made the next day.

 

Q. Will I have garbage service during construction?

A. Yes, your cooperation will be needed to maintain garbage service by putting your container out the morning of and removing your container as soon as possible after it is dumped. There may be times your container will have to be placed on the opposite side of the road. You will be notified by door hanger if you are affected.

 

Q. Will the UTA run on 300 W. during construction?

A. The UTA bus route will follow the traffic detour route.

 

Q. Will my water be interrupted during construction?

A. The portion of this project that involved the replacement of culinary water lines has been completed. There is no expectation of any further water shut-offs.